Royal Victoria Hospital
Belfast,
United Kingdom
A cantilever deck of 30,000m² floor deck slab with concrete-to-floor slab volume of approx. 8,000m³.
400mm thick RC slab with an additional grid of 2.40m x 2.50m concrete beams on top.
Location
Project participants
Customer: NN
The Project
The temporary works provided support to the 14.50m 2-floor element and pvodided a matrix of steel-deck working platforms enabling safe access and close monitoring during massive concrete pours
2.40m deep matrix of reinforced concrete beams
The temporary works provided support to the 14.50m 2-floor element and pvodided a matrix of steel-deck working platforms enabling safe access and close monitoring during massive concrete pours
2.40m deep matrix of reinforced concrete beams
Project Information
"PERI provided a total project solution and delivered excellent quality design."
Michael Lynch
Project Director
Are you building a project like this?
Call us on +966 (0) 11 230 0655 to discuss your requirements further.
Location
Royal Victoria Hospital, United Kingdom