King Abdul Aziz International Airport, Jeddah

Construction of the new Transportation Centre using VARIO GT 24 and PD shoring
Jeddah airport expansion with PERI formwork
Construction of GSE tunnel with PERI VARIO GT 24 and PD 8 slab tables

Project data

Location: Jeddah, Saudi Arabia

The extension of King Abdul Aziz International Airport was one of Saudi Arabia’s biggest airport projects. The capacity was increased to handle up to 30 million passengers per year through a new 640,000 m² terminal building.

PERI delivered formwork for the Ground Services Equipment (GSE) tunnel that connects the aircraft handling area with the cargo village.  Also, the Transportation Centre that connects the passenger terminals and has a total built-up area of 27,000 m² was realized with our formwork.

Requirements

  • Limited on-site storage facilities
  • Large slab areas to be covered
  • Shoring of 14 m high structures 

Customer

Saudi Binladin Group (SBG)

Customer's benefit

  • Detailed formwork design based on extensive track record of airport projects globally
  • Economic formwork solution that minimized training efforts at site
  • Highest level of safety for site staff and ongoing airport operations
  • Reliable logistics that ensured ontime progress 

PERI solution

  • CB 240 climbing brackets with trailing working platforms for finishing works
  • MULTIFLEX to easily adapt to varying slab geometries
  • PD 8 in slab table layout as well as up to 14 m high shoring towers